Business
US$31,7m Kariba Dam rehab nears completion
NewsDay Staff ·

THE US$31,75 million Kariba Dam Rehabilitation Project, funded by the African Development Bank (AfDB), has entered its final phase following the completion of critical safety works, with the remaining spillway upgrades expected to enhance the dam’s long-term reliability.
The project is designed to strengthen the structural integrity of the Kariba Dam, protect millions of people living downstream, and ensure sustained electricity generation for Zimbabwe and Zambia.
AfDB’s March 2026 implementation report rated progress toward the project’s development objectives as satisfactory, noting that most key engineering works have already been completed.
This story is for NewsDay subscribers.